Estimates
| # | Description | Cost Code | Unit Rate | Unit | Qty | Cost Type | Cost | ||
|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 Preliminaries | $458,000.00 | |||||||
| 2 |
01-100
|
$62,000.00 |
item
|
1
|
$62,000.00 |
|
|||
| 3 |
No cost code
|
$9,500.00 |
wk
|
32
|
$304,000.00 |
|
|||
| 4 |
01-100
|
$92,000.00 |
item
|
1
|
$92,000.00 |
|
|||
|
/
|
|||||||||
| 5 | 02-100 Site & earthworks | $286,000.00 | |||||||
| 6 |
02-100
|
$78.00 |
m³
|
2,150
|
$167,700.00 |
|
|||
| 7 |
02-100
|
$46,300.00 |
item
|
1
|
$46,300.00 |
|
|||
| 8 |
02-100
|
$80.00 |
m³
|
900
|
$72,000.00 |
|
|||
|
/
|
|||||||||
| 9 | 03-100 Concrete | $612,000.00 | |||||||
| 10 |
03-100
|
$415.00 |
m³
|
386
|
$160,190.00 |
|
|||
| 11 |
03-100
|
$96.00 |
m²
|
2,400
|
$230,400.00 |
|
|||
| 12 |
03-100
|
$132,610.00 |
item
|
1
|
$132,610.00 |
|
|||
| 13 |
No cost code
|
$88,800.00 |
item
|
1
|
$88,800.00 |
|
|||
|
/
|
|||||||||
| 14 | 05-100 Structural steel | $358,000.00 | |||||||
| 15 |
05-100
|
$6,500.00 |
t
|
42
|
$273,000.00 |
|
|||
| 16 |
No cost code
|
$85,000.00 |
item
|
1
|
$85,000.00 |
|
|||
|
/
|
|||||||||
| 17 | 06-100 Carpentry | $394,000.00 | |||||||
| 18 |
06-100
|
$214,000.00 |
item
|
1
|
$214,000.00 |
|
|||
| 19 |
No cost code
|
$1,250.00 |
ea
|
48
|
$60,000.00 |
|
|||
| 20 |
06-100
|
$120,000.00 |
item
|
1
|
$120,000.00 |
|
|||
|
/
|
|||||||||
| 21 | 07-100 Roofing & waterproofing | $248,000.00 | |||||||
| 22 |
07-100
|
$92.00 |
m²
|
1,850
|
$170,200.00 |
|
|||
| 23 |
07-100
|
$77,800.00 |
item
|
1
|
$77,800.00 |
|
|||
|
/
|
|||||||||
| 24 | 08-100 Windows & glazing | $322,000.00 | |||||||
| 25 |
08-100
|
$2,750.00 |
ea
|
86
|
$236,500.00 |
|
|||
| 26 |
08-100
|
$85,500.00 |
item
|
1
|
$85,500.00 |
|
|||
|
/
|
|||||||||
| 27 | 09-100 Wall & ceiling finishes | $486,000.00 | |||||||
| 28 |
09-100
|
$48.00 |
m²
|
6,200
|
$297,600.00 |
|
|||
| 29 |
09-100
|
$128,400.00 |
item
|
1
|
$128,400.00 |
|
|||
| 30 |
No cost code
|
$60,000.00 |
item
|
1
|
$60,000.00 |
|
|||
|
/
|
|||||||||
| 31 | 15-100 Plumbing | $342,000.00 | |||||||
| 32 |
15-100
|
$168,000.00 |
item
|
1
|
$168,000.00 |
|
|||
| 33 |
15-100
|
$1,400.00 |
ea
|
60
|
$84,000.00 |
|
|||
| 34 |
15-100
|
$90,000.00 |
item
|
1
|
$90,000.00 |
|
|||
|
/
|
|||||||||
| 35 | 16-100 Electrical | $488,000.00 | |||||||
| 36 |
16-100
|
$236,000.00 |
item
|
1
|
$236,000.00 |
|
|||
| 37 |
16-100
|
$152,000.00 |
item
|
1
|
$152,000.00 |
|
|||
| 38 |
16-100
|
$100,000.00 |
item
|
1
|
$100,000.00 |
|
|||
|
/
|
|||||||||
| 39 | 17-100 Mechanical / HVAC | $178,000.00 | |||||||
| 40 |
17-100
|
$178,000.00 |
item
|
1
|
$178,000.00 |
|
|||
|
/
|
|||||||||
| 41 | 31-100 External works & landscaping | $240,000.00 | |||||||
| 42 |
31-100
|
$128,000.00 |
item
|
1
|
$128,000.00 |
|
|||
| 43 |
31-100
|
$62,000.00 |
item
|
1
|
$62,000.00 |
|
|||
| 44 |
31-100
|
$50,000.00 |
item
|
1
|
$50,000.00 |
|
|||
|
/
|
|||||||||
| Estimate total (ex GST) | $4,412,000.00 | ||||||||