Pay

Assess what a subcontractor claims before it becomes a bill

A subcontractor pay application is where a subcontractor claims a period of progress against their subcontract. Bring it into Ledger, assess it line-by-line against the schedule of values, short-pay anything with a documented reason, and certify — which withholds retainage, applies approved back-charges, and writes the assessed payable straight onto a bill.

Pay application #4Acme Concreting · Period to 30 Jun 2026AssessingBecomes a bill on approval
Subcontract
$589,900
03-100 Concrete · retainage 5%
Claimed this period
$165,620
as submitted by the subcontractor
Assessed this period
$158,000
certified against the schedule of values
Schedule of values lineContractedClaimedAssessedVariance
03-100Concrete supply & place$402,000.00$118,500.00$118,500.00$0.00
03-100Reinforcement & formwork
Work not complete
$151,900.00$38,000.00$30,380.00−$7,620.00
03-100Concrete pumping$36,000.00$9,120.00$9,120.00$0.00
Totals line splits reconcile to the $589,900 subcontract$589,900.00$165,620.00$158,000.00$7,620.00
Assessed payable this application
Assessed this period$158,000.00
Retainage (5%)$7,900.00
Back-charges BC-014$2,625.00
Assessed payable$147,475.00
Certify onto billWrites to bill INV-2198

A subcontractor application assessed against the $589,900 subcontract on 03-100 Concrete — claimed line-by-line, short-paid with a documented reason where assessed sits below claimed, with retainage withheld at 5% and an approved back-charge deducted, so the certified $147,475.00 writes straight onto a bill.

Trusted by builders across the country

From custom-home builders to commercial head contractors, teams run their projects on BuildPass.

Reidy Contracting Group
Ameresco
DivisionOne Construction
Fickling Construction
Burkentine Builders
Ready Construction
DD Construction
Southeastern Interiors
Honest Hammer
Homestead
Reidy Contracting Group
Ameresco
DivisionOne Construction
Fickling Construction
Burkentine Builders
Ready Construction
DD Construction
Southeastern Interiors
Honest Hammer
Homestead
Fassberg
AJFX Construction
ECI Austin
JGB Custom Homes
New Age Builder
CDG Construction
PCH Builders
EDG Pro Contractors
Schwartz Custom Homes
ARK General Construction
Fassberg
AJFX Construction
ECI Austin
JGB Custom Homes
New Age Builder
CDG Construction
PCH Builders
EDG Pro Contractors
Schwartz Custom Homes
ARK General Construction

The claim, the assessment and the certificate in one place

01

Assess against the real commitment

Every line is checked against the subcontract's schedule of values, with the assessed-to-date rolled forward from earlier certified claims, so you're never rekeying a running total or reconciling against a separate spreadsheet.

02

Short-pay with the reason on the record

Assess a line below what was claimed and Ledger asks for a reason code and a note before you can certify, so the certified position carries its own justification instead of an email you'll have to find later.

03

Retainage and over-commitment handled at certify

Certifying withholds retainage off the assessed amount against the subcontract's rate and cap, and blocks a claim that would push billed-to-date past the committed value unless you record an audited override.

How it works

Everything a subcontractor pay application needs, from claim to certified bill

Bring the claim in, assess it honestly, and certify it onto a bill.

Bring the claim inDraft
G703Pay application · Acme Concreting
Claimed on cover$165,620.00
Matched to schedule3 / 3 lines
Flagged by AP intake · seeded a draft to review

Bring the claim in

Import a G702/G703 the accounts-payable classifier flagged as a subcontractor claim; Ledger reconciles the cover against the line schedule and seeds a draft to review. Low-confidence documents fall back to manual entry rather than guessing.

Assess line-by-lineClaimed vs assessed
LineClaimedAssessed
Concrete supply & place$118,500$118,500
Reinforcement & formwork$38,000$30,380
Concrete pumping$9,120$9,120
Assess in full seeds at claimed$165,620$158,000

Assess line-by-line

A G703-style grid shows Contracted, Assessed to date, Claimed, Assessed and Variance per line. Enter the assessed amount or a percent complete; “Assess in full” seeds every line at claimed to short-pay down from.

Short-payReinforcement & formwork
Claimed$38,000.00Assessed$30,380.00
Work not completeDefectiveUnapproved variationOvervalued
Formwork to lift 3 not yet stripped — reassess next claim.
Reason and note required · assessed can never exceed claimed

Short-pay with a documented reason

Assessing below the claimed amount reveals a reason picker and note — work not complete, defective, unapproved variation, overvalued and more — both required before you can certify. Assessed can never exceed claimed.

Withhold retainage
Assessed this period$158,000.00
Less retainage (5%)$7,900.00
Net of retainage$150,100.00
On the subcontract's rate · clamped to its cap

Withhold retainage automatically

Certifying withholds retainage off the assessed net on the subcontract's rate, clamped so the held total never breaches the contract's cap. It shows as a distinct “Less retainage” line, never folded into the figure.

Deduct back-chargesApproved
Net of retainage$150,100.00
Less back-charges BC-014$2,625.00
Assessed payable$147,475.00
Pump standby recharge · frozen in after retainage

Deduct approved back-charges

Approved back-charges are frozen into the claim after retention and shown as their own “Less back-charges” deduction, so a set-off is always visible on the record rather than buried in the assessed number.

Certify onto a bill
Bill INV-2198Acme Concreting · 03-100 Concrete · AP
Assessed payable$147,475.00
Certify application
Approval & payment run on the bill · void with a reason

Certify onto a bill

Certifying freezes the assessment, withholds retention, applies back-charges and writes the payable to a bill — where approval and payment run on their own controlled chain. Void a certified claim, with a reason, for the audit trail.

Connected to the whole job

Subcontractor pay applications sit between your subcontracts and your bills

This is the money-out side of Win to Pay. Upstream, the subcontractor pay application claims against the subcontract's cost-coded schedule of values — which also holds the retainage rate and cap and the committed value the assessment is checked against. Downstream, certifying writes the assessed payable onto a bill, and it's the bill that carries the approval, the payment and the drawdown of committed cost on the budget. Where a pay application is what you claim from the client, this is how you assess what a subcontractor claims from you.

Pay application · claimed
$165,620
Acme Concreting · against the $589,900 subcontract on 03-100
assessed & certified
Assessed payable
$147,475.00
retainage $7,900 withheld · back-charge $2,625 deducted
becomes
Bill · AP
INV-2198
draws down 03-100 Concrete budget · approval & payment on the bill

Trusted by builders who run their projects on BuildPass

From custom-home builders to commercial head contractors, teams across Australia and New Zealand run their projects on BuildPass every day.

The onboarding process and training we received from the BuildPass team was fantastic.
Nick Du Bois
Managing Director, FORA
If you're considering implementing new technology on site, you must have BuildPass on your list.
Rob Lineker
Director, Dei One Projects
I'd recommend BuildPass to any builder, sub contractor or site manager. It just makes your life easier.
Garath Vella
Director, Lorden Vella

Frequently asked questions

No login for subs is involved. A subcontractor pay application comes in either as a G702/G703 the accounts-payable classifier flagged, which Ledger parses into a draft, or through your bill intake. “Submit” is your own action — it freezes the claimed amounts and starts the served clock so you can begin assessing.

Yes. Assess any line below the claimed amount and Ledger requires a reason code and a note before you can certify, modelled on a payment-schedule obligation. What it won't let you do is assess a line above what was claimed.

Retainage is withheld automatically when you certify — off the assessed net, on the subcontract's rate, and clamped to its cap — and shown as its own deduction line. Releasing retainage later is handled on the retainage register, not from the claim.

Certifying freezes the assessment, withholds retention, applies any approved back-charges, and writes the assessed payable onto a bill. Approving and paying that bill happen on the bill's own approval chain — this step assesses and certifies, it doesn't move the cash.

No — it's the buy-side mirror. A pay application is the claim you make to your client (money in); a subcontractor pay application is a claim a subcontractor makes to you (money out), which you assess and certify before it's paid.

Assess your next subcontractor pay application in BuildPass

Subscribe for BuildPass news and product updates, or book a demo to see this on your own subcontracts.